Underground crossing is getting closer. Warsaw is building a tunnel under the tracks

inzynieria.com 2 months ago

The tunnel under the tracks will have 180 m long. It features a carriageway with 2 lanes, a one-sided pavement and a bicycle path. West of the underground crossing will emergence new platforms.

Besides, the task is to build 3 roundabouts:

  • at the intersection of 1st Prague Regiment, Władysław Sikorski and Jan Kiliński
  • on Okuniewska Street on the western side of the tunnel
  • connecting 1st Street of the Prague Regiment to the Polish Military Square.

During the works there will be a temporary crossing to Żółkiewskiego Street, between Wola Grzybowska and Warsaw Wesoła. That's where the work starts. The contractor that Warbud became will be at the construction site at the latest Two months. Then there will besides be a temporary crossing at the level of rails on the east side of the Warsaw Wesoła halt and a temporary platform at the track towards Rembertów.

Contract value PLN 93.9 million. It will be financed by the first mentioned entities after half. I want everything ready in 28 months.